Eversleigh Road, Scarborough

Projex Partners was engaged by Moreton Bay Regional Council to undertake a site investigation, geotechnical investigation and slope stability assessment of the existing embankment for the removal of a large tree at the eastern end of Eversleigh Road, Scarborough.


Projex Partners worked with Council to solve the slope stability issues and improve the useability of the site through the construction of a retaining wall and landscaping.

Callaghan Park Boat Ramp, Rockhampton

As part of the Fitzroy Boat Ramp project, Projex Partners delivered directly to Rockhampton Regional Council, the design and contract administration for the boat ramp carparking facility at Callaghan Park in Rockhampton.


This new 4-lane boat ramp onto the Fitzroy River has a floating walkway, 52 car and trailer parks, 15 car only parks and loading and unloading areas.

Stanage Bay Boat Ramp Reconstruction

Projex Partners was engaged by Transport and Main Roads (TMR) to undertake the detailed design and construction administration of the replacement of the boat ramp at Stanage Bay.

The Stanage Bay boat ramp replaced the existing ramp with a new two lane ramp, floating walkway and groyne to provide safer access to the Thirsty Sound passage during all weather events.


Mulambin Causeway Lake Boat Ramp Reconstruction

Projex Partners was engaged by Transport and Main Roads (TMR) to undertake the detailed design and construction administration of the replacement of the boat ramp at Mulambin Causeway Lake on the Capricorn Coast near Yeppoon.


The Mulambin Causeway boat ramp replaced the existing ramp with a new single lane ramp to access the Mulambin Lake.

Ski Gardens Boat Ramp Upgrade, Rockhampton

Projex Partners was engaged by Transport and Main Roads (TMR) to undertake the detailed design and construction administration of the replacement of the boat ramp at Ski Gardens on the Fitzroy River in Rockhampton.


The Ski Gardens boat ramp replaced the existing ramp with a new two lane ramp to access the ski and fishing areas upstream of the Fitzroy River weir.

Glebe Weir Boat Ramp Upgrade, Spring Creek

Projex Partners was engaged by Transport and Main Roads (TMR) to undertake the detailed design and construction administration of the replacement of the boat ramp at Glebe Weir on the Dawson River near Theodore.

The Glebe Weir boat ramp replaced the existing ramp with a new single lane ramp to access the ski and fishing areas upstream of the weir.

Starboard Drive Boat Ramp, Bowen

Projex Partners was engaged by Transport and Main Roads (TMR) to undertake the detailed design and construction administration of the upgrade and widening of the public boat ramp in the Bowen boat harbour at Starboard Drive.


Starboard Drive boat ramp included the modification and upgrade to the existing ramp including widening of the existing boat ramp to incorporate a new eastern lane, extension of the western lane and the provision of a floating walkway.

Horseshoe Bay Boat Ramp, Bowen

Projex Partners was engaged by Transport and Main Roads (TMR) to undertake the detailed design and construction administration of the replacement of the boat ramp in Bowen at Horseshoe Bay Road.


The Horseshoe Bay boat ramp replaced the existing ramp with a new two lane ramp to access the ocean north of Bowen.

Mooloolaba Sandbag Wall – Stage 2 (Design & DA)

Projex Partners was engaged by Sunshine Coast Council to design, document and certify a buried sandbag retaining wall at Mooloolaba Spit (Parkyn Parade) to protect the beach and park infrastructure against erosion from major weather events.

Mooloolaba Spit is an important part of the Sunshine Coast’s beachside environment for tourists and locals, however ongoing erosion during severe weather events has caused significant scarping and damage to vegetation and park infrastructure that is impacting the amenity of the beachfront and threatening existing infrastructure.

The sandbag wall will work in conjunction with the Mooloolaba sand pumping program to improve the amenity of the beach and limit the impacts of future weather events.

Bradman Avenue Revetment Wall, Maroochydore

Sunshine Coast Council requested Projex Partners undertake detailed design of a grouted rock pitched revetment wall to replace an existing failing section (approximately 42m) of the revetment wall along Bradman Avenue.